Secondary Building Project

Feasibility Study

The results of the feasibility study are now available. Please click here to access the report and addenda, including the third-party demographic study.

You can also click here to see the latest presentation regarding the feasibility study.

The Feasibility Study Process

Weston High School and Weston Middle School have reached the stage in their life cycle where the town and district must evaluate the current state of the buildings and determine the best and most fiscally responsible means to move forward, all while ensuring Weston Schools are able to offer the same caliber of excellence for years to come.

The Town of Weston has engaged an architect, Lavallee Brensinger, to develop a master plan for the Weston Middle/High School Campus. The reasons for conducting the study include, among others:

  • Several building systems are aging and need replacement—should the town renovate or rebuild?
  • Schools lack adequate small group spaces, and some classrooms fall below state size recommendations.
  • Enrollment is expected to grow 20-40% over the next decade.
  • Recreation and athletics need upgrades, including the pool.
  • The Middle and High Schools are the town’s biggest energy users — efficient, fossil-fuel free systems are needed to meet climate goals

This study will consider a range of options including renovating the existing schools with no additions or changes in program; renovating the existing schools with additions; and building a new school or schools. Options with and without MSBA funding will be considered.

For a complete picture of feasibility study through November 2024, we invite you to review the Fall 2024 HS/MS Campus Feasibility Project Background And Update.  The presentation is also available in full via Weston Media’s recording of the December 16, 2024, School Committee meeting.  The presentation begins 11 minutes, 30 seconds into the recording.

More information regarding the different aspects of the feasibility study is available below:

A feasibility study, and building projects in general, require a highly collaborative process and cannot be successful with the input of the community.  If you are interested in participating, please keep an eye out for an email from the Office of the Superintendent requesting volunteers. Depending on the stage of the process, the district may prioritize community members with direct experience with the current middle and high school facilities; however, we hope to garner feedback from every corner of this community by the end.  

Video: Principal Coffee Recording April 8, 2025

Principal Coffee Presentation: Master Plan Alternatives

May 12 Community Presentation: Master Plan Alternatives with Costs

In addition to specific forums and working groups, we will be hosting four community meetings over the course of the feasibility study and all are encouraged to attend.  The current schedule is as follows:

Event Date Time Location
Community Meeting 1: Project Charter Presentation January 29, 2025 5:00 – 7:00 p.m. HS Cafeteria
Community Meeting 2: Master Plan Alternatives
At this meeting, the architects will present high-level options for renovations and new construction for Weston Middle School, High School, and pool. The architects will ask for feedback on the options, specifically about whether renovation or new construction are preferred, and about which project should be completed first.
March 4, 2025 11:00 a.m. – 12:15 p.m. Case House Large Conference Room
Community Meeting 3: Master Plan Options and Costs

At this meeting, the architects will present options for renovation and new construction for the Middle School, High School, and Pool, along with cost estimates for each option. The architects will ask for feedback about which option is preferred.

May 12, 2025 7:00 – 8:30 p.m. Zoom [Click here]

Community Outreach

During their annual summer retreat, the School Committee opted to dedicate the 2025-2026 school year to engage with the greater community, educating them on the potential pathways available to the town and soliciting feedback on the options presented in the feasibility study.

On December 12, 2025, Weston Public Schools was invited to join the Massachusetts School Building Authority’s (MSBA) Eligibility Period, shifting the focus of the project toward this funding pathway. The MSBA’s program is highly structured by design and community outreach will continue in accordance with their timelines.

Meetings and Materials

Event Date Time Location Materials
Community Meeting 1 October 23, 2025 6:00 – 7:30 p.m. Case House Large Conference Room Presentation
Community Meeting 2
October 30, 2025 7:00 – 9:00 p.m. Remote [Link] Presentation

MSBA Eligibility Program

The Town of Weston was invited to join the Massachusetts School Building Authority’s (MSBA) Eligibility Period on December 12, 2025. As explained by School Committee member Ken Newberg at their December 15 meeting, the district took a multipronged approach to the building project, with all work to date serving as preparation for either a self-funded path or one seeking MSBA reimbursement. If accepted into the MSBA’s full program, the town is projected to be eligible for a reimbursement rate of at least 31%.

The 270-day Eligibility Period is designed to formalize and streamline the start of the MSBA grant approval process. For the Town, this phase provides a clear and predictable timeline for completing preliminary requirements, helps assess both financial and community readiness, and identifies key considerations for future planning and budgeting. Successfully completing all activities during the Eligibility Period positions the Town to be eligible for an MSBA invitation to proceed to their Feasibility Study.

Eligibility Period Timeline and Deliverables

The timeline for the MSBA’s Eligibility Period is determined by the organization, based on the district’s assigned date of commencement. As deliverables are completed, they will be included in the below table, linked to the document’s title.

Deliverables Days from Commencement  Due Date
Eligibility Period Commences Wednesday, April 1, 2026 
Initial Compliance Certification 30 Friday, May 1, 2026
School Building Committee 60 Monday, June 1, 2026
Educational Profile Questionnaire 90 Tuesday, June 30, 2026
Online Enrollment Projection 90 Tuesday, June 30, 2026
Enrollment Meeting Held 180 Monday, September 28, 2026
Maintenance and Capital Planning Information 180 Monday, September 28, 2026
Local Vote Authorization 270 Monday, December 28, 2026
Feasibility Study Agreement 270 Monday, December 28, 2026
Eligibility Period Concludes Monday, December 28, 2026