August 18, 2017 Field #1 should be ready for the beginning of fall High School sports. The old carpet was removed, base material regraded. New shock pad was installed and new carpet with inlaid lines has been installed. The final work is to finish the sports lines, add the infill material, and secure the new carpet.

August 17, 2017 Proctor Field Renovations are on schedule. The old field and related equipment was removed in early June. Site work continues with the installation of drainage, field lights, net pole bases, new concrete pad for visitors bleachers, and track and field structures. The new concession/bathroom building is on schedule as well. The building footprint has been excavated, the frost walls have been poured.